Divi Resort Vista III

Aruba

Project Stats

Type: Resort Hotel
ICF Use: 85,400 sq. ft.
Cost: $20 million
Total Project Construction Time: 80 weeks
ICF Installation Time: 120 days

Construction Team

Owner: Divi Resorts
General Contractor: Gemini Contractors
ICF Installer: Gemini Contractors
Architect: IXI Design N.V.
ICF Consultant: Tim Viau
ICF System: Nudura

On Eagle Beach in Aruba, an ICF resort addition was built using Nudura® Insulated Concrete Forms (ICFs) to provide occupants an energy efficient, safe and gorgeous Caribbean getaway. The new Vista III wing of Divi All Inclusive Resorts added 60 luxury rooms that maximize comfort and protect visitors and staff from extreme weather conditions.

By maintaining interior temperatures and limiting the need for HVAC usage, ICF construction offers ongoing financial savings for the owners. The concrete-filled blocks are easy to install and speed construction timelines. For this waterfront resort, Insulated Concrete Forms helped them achieve all their goals, highlighting how ICFs advance the hotel and hospitality industry by improving quality and sustainability while minimizing labor and operational costs.